Complete Renovation & Alterations of Grade II Listed Property

This project started in March and completed in August 2017 and consisted of the following works:-

  • complete rewire
  • complete re-plumb and installation of central heating system
  • structural roof repairs and re-roof
  • supplying and installing  diamond stone mullions to window sets and walling up doors to form windows apertures
  • supply and installtion of new Hardwood doors and sliding sash windows
  • removing loadbearing walls and installing steelwork as required
  • damp proofing
  • re-pointing the external elevation with lime mortar
  • removing all internal wall and ceiling finishes, renewing ceilings and plastering all external walls with a traditonal 3 coat horse hair and goat hair lime plaster system
  • new floors and staircase
  • new bathrooms and kitchen