Conversion of Farmhouse & Attached Cottage, Disabled Adaption Works & Pool

This project was started in November 2016 and is due for completion in November 2017, the project consists of the following works:

  • demolishing porch, garage and rear extension
  • creating new driveway and drystone retaining walls
  • raising and lowering floors to create one level through the property
  • altering structural openings
  • underpinning
  • constructing a two storey extension
  • cladding brick walls with reclaimed stone
  • glass walls, Glulam beams and glass roofs to pool room and sitting room
  • insulating external walls and plastering
  • structural re-roofing works
  • construction of hydrotherapy pool
  • first and second fix plumbing including bathrooms and kitchens
  • first and second fix electrics including sono's sound system throughout the property
  • insulated under floor heating system to the whole of the ground floor and floor finish
  • constructing a lift shaft with open fire and floating staircase
  • plastering
  • first and second fix joinery
  • renewable technologies such as PV Panels, Ground Source Heat pumps including all groundworks
  • external landscaping , drystone retaining walls and removal of trees.
  • new tarmac drive and parking area